Sunday, August 10, 2008

Bar, Lounge & Restaurant

During May the concrete slabs for the bar, lounge and restaurant were completed. In order to deal with the varying levels between sections and buildings as well as aesthetic purposes, the concrete was poured 'within' a perimeter of small shaped volcanic rocks. This then also hides the level of concrete from view when the buildings are seen from the outside as the walls will be erected inside but against the edge of this little rock perimeter.


The photos below show clearly how big the difference in levels between sections and buildings really is.



From foreground to back: edge of bar, lobby from reception, lounge, restaurant to far left and bathrooms serving restaurant and lounge to the far right.
Bar and recreation area (far left) - looking across to where the campfire area will be

Sunday, January 13, 2008

Photo Updates (3) - Foundations

Reception seen from the office side




Reception foundations seen from the lobby exit that will lead to the restaurant, lounge and bar. Main reception in the foreground with the office at the furtherest end.







The foundations completed of the bathrooms for the crew/guide rooms







Completing the foundations of the Crew/Guide roomsAll the foundations being done with volcanic rock as well

Photo Updates (2) - Foundation trenches

The trenches for reception, shop and bathrooms




Restaurant, Lounge and their bathrooms trenches dug and ready for foundations

Thursday, February 08, 2007

1st Foundations

Foundations commence at Safari Tent sites
A very happy day indeed. The first foundations were started today being the foundations for the supports of the safari tents and and the rock bathrooms.

The supports will first be erected after which the bathroom foundations proper will be dug. These foundations will then incorporate four of the supports' foundations. There are 12 support uprights in the planning which will support the tiled roof over the safari tent and bathroom.